Quick answer
In Herriman, a tear-off reroof, a deck more than 30 inches high or under a new roof, a water heater, furnace or AC replacement, a fence over 7 feet, and a retaining wall holding 4 feet or more of fill all need a permit. Apply with the city's online permit application form and call 801-446-5327 before 4 p.m. to book an inspection. Homes in the city's wildland-urban interface zone may face added fire code requirements.
Herriman's Building Department is at City Hall, 5355 West Herriman Main Street, open 7:30 a.m. to 5:30 p.m., Monday through Friday. Call 801-446-5327 or email [email protected] (Building Permits). The city's position is short: most construction work needs a permit and inspections.
How to apply
Herriman takes permits through an online Permit Application Form linked from each project page. Attach the documents the project page lists. The city emails an invoice, and the permit issues after plans are approved and fees are paid. Plan review for most projects takes about 10 to 15 working days.
Inspections run Monday through Friday, 8 a.m. to 4:30 p.m., with no weekend inspections. Call 801-446-5327 before 4 p.m. for an inspection the next business day or later (Building FAQs).
What needs a permit
Roofs (Re-Roofs). Removing all shingles down to the sheathing needs a permit ($119.18 as listed in November 2026) and two inspections: a timed mid-roof inspection after tear-off, flashing and ice and water shield, with the contractor on site, and a final. Adding one layer over existing shingles needs no permit, but two layers is the maximum. If solar panels come off and go back exactly as they were, say so on the application; if the array changes, the solar installer needs a separate solar permit.
Decks (Decks). A permit is needed if the deck is more than 30 inches above grade, will have a new roof over it at any height, or serves the front door. Attached decks need post footings at least 30 inches deep. The fee for a deck without a roof was $432.39.
Water heaters, furnaces and other trade work (Electrical/Mechanical/Plumbing). A permit is needed to:
- replace or add a furnace, air conditioner or water heater
- install any fireplace
- add new electrical, mechanical or plumbing lines to the home or a detached structure
- install a backyard gas fire pit, a generator or Generlink, or an EV charger circuit
Repair and maintenance of existing systems does not need one. A basic permit is $101; gas appliances, fireplaces, generators and EV chargers need a plan review, which brings the total to $284. An adult must meet the inspector.
Fences (Fences). Fences 7 feet or shorter need no building permit; taller ones need one, with engineer-stamped details. Height limits still apply: 3 feet for a solid front-yard fence, 4 feet for an open one, and 8 feet in side and rear yards. The city does not enforce HOA rules or CC&Rs, so check those yourself.
Retaining walls (Rock/Masonry Walls). A rock or masonry wall holding 4 feet or more of unbalanced fill needs a permit, and so does a shorter wall holding a surcharge. Plans need a Utah-licensed geotechnical engineer's stamp, and the engineer or a special inspector must certify the finished wall; the permit stays open until that letter arrives. The residential fee is $304.02. Rock walls can't go in the front utility easement.
Wildland-urban interface and fire access
Herriman has both city and state wildfire rules to know about:
- City WUI zone map. On September 9, 2026, the city council adopted Ordinance 2026-18, amending the city's fire code section (4-1-1) and adopting the 2026 Herriman City Wildland Urban Interface Zone Map.
- New homes. The city's single-family dwelling page says added fire code requirements may apply to a home in an urban-wildland interface area (citing Utah Code 15A-5-203), on a lot without fire hydrant coverage, or where the only fire access road is steeper than 10% for more than 500 feet. New homes also need a soils report on site for the footing inspection.
- State HB 48. The city's Utah WUI Program page explains that the Utah Division of Forestry, Fire and State Lands is drawing a statewide high-risk boundary, published on the Utah Wildfire Risk Assessment Portal. Properties inside it may owe an annual fee set by the state and collected by Salt Lake County; Herriman does not set or collect it.
If you are building or adding on near open land, ask the Building Department whether your lot is in the WUI zone before you take bids, so contractors price any added fire-resistance work up front.
Open burning is not allowed at Herriman homes, and wood fire pits need no permit but must meet fire code clearances (Building FAQs).
Owner-builders
Herriman's Owner/Builder Declaration page says an owner-builder on a residential permit acts as their own general contractor and takes responsibility for all the work. You sign a notarized Owner-Builder Certification and Agreement to Comply; for a new house you also sign a Homeowner Power to Panel Agreement and a Homeowner Grading Agreement. You may build one house per calendar year and no more than three in five years, and the city registers you with DOPL when it issues the permit, as Utah Code 58-55-305 requires. Owner-builder is not allowed on commercial work.
Building without a permit
The city's FAQs list the consequences: the permit fee doubles, daily penalties can apply until the work complies, work that violates city ordinances may have to be removed, licensed contractors can face state penalties, and insurance may not cover damage from unpermitted work.
Check the contractor
Herriman tells residents to verify licenses and file complaints through DOPL. Use DOPL's license search. Generally only the licensed general contractor pulls the permit and lists the electrical, plumbing and mechanical subcontractors on the application. Jobs under $7,000 can fall under the handyman exemption in Utah Code 58-55-305(1)(h), but plumbing and electrical work still needs licensed trades and HVAC work a licensed HVAC contractor. The Utah licensing guide has the details.
Before you sign
- Confirm the license number and classification.
- For a reroof, ask whether it is a tear-off (permit) or an overlay, and who will be on site for the mid-roof inspection.
- For a retaining wall, confirm the geotechnical engineer and special inspector are in the price.
- Ask about the WUI zone for any new home or addition near open land.
- Review Utah lien law and collect lien waivers before final payment.
The hiring checklist and Utah building permit requirements cover each step. Nearby, see Riverton and South Jordan, or all of Salt Lake County. Browse Herriman plumbers, electricians, HVAC contractors, roofers, window and door installers and remodelers.
Sources
- Herriman, Building Permits: address, hours, phone, email, inspection requests.
- Herriman, Building FAQs: inspection hours, who pulls permits, penalties, fire pits, open burning.
- Herriman, Re-Roofs.
- Herriman, Decks.
- Herriman, Electrical/Mechanical/Plumbing.
- Herriman, Fences.
- Herriman, Rock/Masonry Walls.
- Herriman, Single-Family Dwellings: WUI, hydrant and access-road triggers, soils report.
- Herriman, State of Utah Wildland-Urban Interface Program: HB 48 boundary and fee.
- Utah Public Notice, Herriman Ordinance 2026-18: 2026 WUI Zone Map.
- Herriman, Owner/Builder Declaration.
- Utah Code 58-55-305: owner-builder and under-$7,000 exemptions.
- DOPL license lookup.
Frequently asked questions
Do I need a permit to replace my roof in Herriman?
If the shingles come off down to the wood sheathing, yes: Herriman requires a permit and two inspections, including a mid-roof inspection with the contractor on site. Adding one layer over existing shingles needs no permit, but no more than two layers are allowed.
Do I need a permit for a water heater or furnace in Herriman?
Yes. Replacing or adding a furnace, air conditioner or water heater needs a permit. Repair and maintenance of existing systems does not.
Is my Herriman home in a wildland-urban interface area?
The city council adopted a 2026 Herriman City Wildland Urban Interface Zone Map with Ordinance 2026-18 on September 9, 2026. Ask the Building Department (801-446-5327) whether your lot is in the zone. Separately, the state's high-risk boundary under HB 48 is published on the Utah Wildfire Risk Assessment Portal.
Can I build my own home in Herriman?
Yes, by declaring yourself owner-builder on a residential permit. You sign a notarized Owner-Builder Certification, may build one house per calendar year and no more than three in five years, and the city registers you with DOPL when the permit issues.